Exclusive news and data that keep market professionals aheadWednesday, October 21, 2026

Yadadri thermal power station's fifth 800 MW unit synchronised with grid

Nalgonda, Oct 21 (UNI) Telangana Power Generation Corporation Limited (TGGENCO) achieved a major milestone with the synchronisation of the fifth 800 MW unit of the Yadadri Thermal Power Station (YTPS) with the power grid at 1106 am on Tuesday. The unit was subsequently taken off the grid for further commercial operation date (COD)-related activities. The 4,000 MW YTPS project, located at Veerlapalem village in Damaracherla mandal of Nalgonda district, comprises five units of 800 MW each. Four units have already been commissioned and brought into commercial operation, while work is progressing towards the commercial commissioning of the fifth unit. TGGENCO…

News Details

Words:
100
Type:
TEXT
Slug:
ENERGY TELANGANA YTPS
Source
UNI India
Category
,
Published At
21/10/26 09:14
Last updated
21/10/26 09:14
Location
Nalgonda, India