Yadadri Thermal Power Plant Unit-5 synchronised with grid in T'gana: KTR
Published: 20/10/26 13:31
Hyderabad | India
Hyderabad, Oct 20 (UNI) BRS working president K T Rama Rao today said the Yadadri Thermal Power Plant had achieved another milestone with the successful synchronisation of its 800 MW Unit-5 with the power grid. In a post on social media platform X, KTR said the 4,000 MW mega project was envisioned by former Chief Minister K. Chandrashekar Rao (KCR) and backed by a Rs 20,400 crore order to BHEL. He described the project as a symbol of Telangana's power sector transformation, noting that the State's installed power generation capacity had increased from 7,778 MW in 2014 to nearly 20,000…