Friday, Apr 26 2024 | Time 01:43 Hrs(IST)
image
Business Economy


BHEL commissions 600 MW Thermal Unit in Telangana

New Delhi, Jan 5 (UNI) Bharat Heavy Electricals Limited (BHEL) today commissioned the first 600 MW coal-based thermal power plant in Telangana.
The unit, commissioned at Kakatiya Thermal Power Project (TPP) at Chelpur in Warangal District of Telangana, is the highest rating unit in the state. One coal-based unit of 500 MW rating, commissioned by BHEL in 2010, is already operational at Kakatiya TPP,said the company.
BHEL-built 600 MW rating sets comprise a four cylinder turbine, which is designed in-house, amply demonstrating the engineering prowess of BHEL. So far, it has contracted 21 sets of 600 MW each, out of which 14 have already been commissioned. A large number of similar sets ensure easy availability of spares and operator's familiarity,it added.
It has a major contribution in Telangana's Power Sector, with 84 per cent of the coal-based power stations, amounting to 4,580 MW, having been commissioned by BHEL.
The company has executed 500 MW unit at Kakatiya TPP of TSGENCO ranked first with a Plant Load Factor (PLF) of 93.75 per cent among all state sector power stations in 2014-15.
Projects equipped with BHEL-supplied sets such as Kothagudem and NTPC's Ramagundam in Telangana have continuously been winning meritorious awards from the Ministry of Power for outstanding performance, said BHEL.
The orders include four units of 270 MW at Bhadradri, one unit of 800 MW at Kothagudem and five units of 800 MW rating each at Yadadri. In addition to this, two units of 600 MW each at Singareni thermal power project at Pegadapally, being set up by Singareni Collieries Company Limited (SCCL) are also being executed by BHEL in Telangana. All these power plants are expected to commence generation on fast track basis to meet the demand for power aimed at providing an impetus to the development of the state.
The company has established its engineering prowess by successfully delivering higher-rated units such as 600 MW, 660 MW and 800 MW thermal sets, having a high degree of indigenisation,it added further.

UNI RN RSA 1315
More News

Arun Alagappan appointed as Executive Chairman of Coromandel International

25 Apr 2024 | 7:41 PM

Hyderabad, April 25 (UNI) Arun Alagappan has been appointed as Executive Chairman of Coromandel International Limited (CIL).

see more..

Tech Mahindra net at Rs 661 crore in Q4; Company gives dividend of Rs 28 per share

25 Apr 2024 | 7:28 PM

New Delhi, April 25 (UNI) Mahindra Group company Tech Mahindra, a technology consulting and digital solutions provider, on Thursday reported about 41 per cent decline in net profit at Rs 661 crore year-on-year basis for the fourth quarter ended March 31, 2024.

see more..

Kottayam-Kochi Rubber Market Rates

25 Apr 2024 | 7:26 PM

Kottayam, April 25 (UNI) Following were the Rubber Market rates announced by the Rubber Board here today per quintal.

see more..
Indusind Bank net up 15 pc in Q4

Indusind Bank net up 15 pc in Q4

25 Apr 2024 | 7:10 PM

New Delhi, April 25 (UNI) Leading private bank Indusind on Thursday reported a 15 percent jump in net profit at Rs 2,349 crore in Q4 of FY 2023–24, compared to Rs 2,043 crore in the same quarter in 2022–23.

see more..

25 Apr 2024 | 6:53 PM

New Delhi, April 25 (UNI) Leading private bank Indusind on Thursday reported 15 percent jump in net profit at Rs 2,349 crore in Q4 of FY 2023-24 compared to Rs 2,043 crore in the same quarter in 2022-23.

see more..
image